So, let me talk about the easy stuff first. One of the best things that can happen to a Scrum Team is that it finishes its work early in a Sprint. It amazes me that Teams are confused about what to do, but they are. So here goes… If the Team finishes early, it seems to me there are two choices: take a holiday, or do something new.

scrum team finishing sprint earlyI have seen Teams take a half-day off if that’s all the time they have left, and I applaud this. In most cases, however, the Team should just bring something new into the Sprint and do it. By definition, the Items near the top of the Back Burner are Stories that are no more than one short conversation away from being agreed to; that is, the Team needs a short conversation before it can start work on one of them. So, the Team should work with its Product Owner to figure out which Story on the Back Burner to do. Maybe it’s something the Product Owner wants, or maybe the Team gets to work on one of the Chores (like some refactoring or something) that has been put off until later. It should be one that the Team thinks might fit into the time remaining in the Sprint, so they finalize the Doneness Agreement, task it out, and just do it.

Yes, it is really just that simple… unless the Team can’t find one that will fit in the time remaining in the Sprint. Then the Team can do one of two things: take a holiday, or just start a new Story, knowing that it will spill over into the next Sprint. In this second case the Story is actually part of the next Sprint, not this one. Now, that really wasn’t so hard, was it?

Learn More in Dan and Doug’s Book: Exploring Scrum: the Fundamentals: People, Product, and Practices

Tagged with →  

2 Responses to What Do You Do When You Finish a Scrum Sprint Early?

  1. rlpmjp says:

    Rather than bring something new into the Sprint, we have just started on the next Sprint’s work.  That Sprint or the one after that can get re-balanced at the next Sprint Planning Meeting.

    • 3Back says:

      rlpmjpWell, since you can’t know what the next sprint’s work is until you have the planning meeting, then you are just bringing new stuff in. If you have future sprints already planned out, that is a sign of misunderstanding of scrum. You plan one sprint at a time, so there is nothing that already belongs to the next sprint.